A test train has already passed through the renovated tunnel between the Lybidska and Demeevska stations.
Kyiv Metro
The owner of the company “, the contractor for the repair work on the section between the Lybidska and Demeevska stations in the Kyiv metro, announced specific dates for the restoration of full-scale traffic on the Obolonsko-Teremkovskaya branch.
According to “Ekonomicheskaya Pravda”, Maksym Shkil predicts that all tests will be completed by September 10. If no problems arise, this means that starting September 15, Kyiv residents will be able to get to the Goloseevsky district of the capital without any interference.
On the night of August 21, a test train passed through the reconstructed tunnel for the first time, testing the dimensions of the section – there were no comments. The installation of cables and telecommunications is expected to be completed by August 29. After that, it remains to ensure the safety of movement at speed and the reliability of the rails.
- Due to the flooding of the tunnel and the closure of traffic on the “Lybidska” – “Demiivska” section, officials of the Kyiv metro were suspected of official negligence.